Project work to the end of the year

We still have a long list of jobs to tackle, so there will be working parties most weekends. Please come and join us if you can spare a few hours:

18/19 November – Installing fibre all the way down Station Road
23-25 November – Station Lane – Completing preparations for fibre to be installed under the level crossing
1 December – TVEC – Preparing chamber for Network Rail fibre
7 December – Longmead Drive – Two chambers to install
+ various other jobs completing ducting to houses and general tidying up.
Preparing for fibre along Main Street, Fiskerton.

Future plans will then include trenching on The Village Green and Claypit Lane, as well as filling in around the above. Anyone fancy leading a working party to accelerate these sections of the project?

Thanks

The F4RN Team.